KINGDOM OF SAUDI ARABIA
GENERAL AUTHORITY OF CIVIL AVIATION
SAUDI AIR NAVIGATION SERVICES
AERONAUTICAL INFORMATION MANAGEMENT
P. O. BOX 929, JEDDAH - 21421
|
|
| |
|
|
| |
AIP
SUP
AIP SUP 21/26
18 MAY 2026
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
OEJN — JEDDAH / KING ABDULAZIZ INTL AIRPORT – Unit Load Device (ULD) Project at Apron Bravo (B)
|
|
|
The purpose of this AIP Supplement is to inform aircraft operators about the construction works related to the Unit Load Device (ULD) project located at Apron Bravo (B) at King Abdulaziz International Airport (KAIA).
|
2 Timeframe for the installation/construction activities
|
The period of the Construction activities of the ULD Project on Apron B. These activities are divided as
follows:
Project
Phases
|
Activity
|
Estimated
Duration
|
Consequence
|
Remark
|
|
Phase 1
|
Design |
+ 6 weeks |
The operational impact of the project involves utilizing the bus parking stands located west of
Taxiway L. During the construction phase, an area of approximately 2,000 m2 will be reserved for the
execution of the works, including the construction of a building with an area of 1,300 m2, situated west of Taxiway K within Apron B.
|
All phases
would be
announced by
NOTAM.
|
|
Phase 2
|
Manufacturing |
+15 weeks |
|
Phase 3
|
Transportation |
+ 4 weeks |
|
Phase 4
|
Installation |
+ 9 weeks |
|
Phase 5
|
Testing &
commissioning
|
+ 2 weeks |
|
3 Areas affected during the work in progress:
|
|
Working Area
|
|
Points
|
Coordinates
|
Height above ground level
|
Elevation above
mean sea level
|
Equipment
|
|
1
|
21°39'54.74"N 39°10'01.96"E |
7 m |
14 m |
Crane |
|
2
|
21°39'55.00"N 39°10'02.66"E |
7 m |
14 m |
Crane |
|
3
|
21°39'53.31"N 39°10'03.32"E |
7 m |
14 m |
Crane |
|
4
|
21°39'53.08"N 39°10'02.62"E |
7 m |
14 m |
Crane |
|
5
|
21°39'55.26"N 39°10'03.56"E |
15 m |
22 m |
Crane |
|
4 Activation of the AIP supplement:
|
NOTAM will be issued to activate phases.
|
5 Replacement or cancellation of the AIP SUP:
|
Any significant change in the current information would be notified by replacement AIP SUP.
This AIP Supplement will remain effective until further notice, and NOTAM will be issued to announce the cancellation of this AIP SUP.
|
|
|
For any inquiries, please contact:
|
Aerodrome / SANS
|
CONTACT DETAILS
|
|
Jeddah TWR
|
Name: JED Tower
Email: jedtwr@sans.com.sa
|
|
Aerodrome Operator (JEDCO)
|
Name: Adil Abdo
Email: aabdo@jeddahairports.sa
|
|
Aerodrome Operator (JEDCO)
|
Name: Moataz Faraj
Email: mafaraj@jeddahairports.sa
|
|
OEJN AD SUP 21-26
|